top of page

LTA CRL CR203

Design and Construction of Turf City Station and Tunnels for Cross Island Line

Client:         
Contract:   
Location:   
Period:    
Land Transport Authority
Design and Build
Turf City, Singapore
2024 - 2032
5.8m I.D.
3,000m
Slurry TBM Machine
Bored Tunnels

Contract CR203 involves the design and construction of an Underground CD station Turf City Station and a 3km bored tunnel towards CR205 King Albert Part Station.

The tunnel will be constructed with two slurry TBM. The contract also comprises a TBM launch shaft and a new road connecting the Station to Eng Neo Avenue.

Related Projects
T225_Substantial Completion_edited_edite

Design and Construction of Bored Tunnel between Fairways Drive and Sin Ming Walk

CR202
Cross Island Line
T305_Concourse_1_edited_edited.jpg

Design and construction of 6-km long tunnels between Aviation Park Station and Changi East Depot.

CR102
Cross Island Line
bottom of page