top of page
T316
Underground Infrastructure
Changi Airport
Twin bored tunnels from Changi Airport Terminal 5 to Changi Airport (CGA) Station Terminal 2
LTA DTL3 C923A
Construction of Tunnels between Tampines East and Upper Changi Stations
Client :
Contract :
Location :
Period :
Land Transport Authority
Build
Tuas, Singapore
2011 - 2016
6.73m
EPB Machine
4,760m
Bored Tunnels
1/3
The Downtown Line Stage 3 C923A project include the construction of tunnels between Tampines East and Upper Changi Stations with a total length of 4.76km, a TBM launching shaft and eight cross passages. Two 6.35m diameter EPB machines were used to construct the bored tunnels.
C923A Awards
2013
LTA ASAC Accident Free Recognition Award
bottom of page