Design and Construction of Turf City Station and Tunnels for Cross Island Line

Client :
Contract :
Location :
Period :
Land Transport Authority
Design and Build
Turf City, Singapore
2024 - 2032
7.24m
Slurry TBM Machine
3,000m
Bored Tunnels

Contract CR203 involves the design and construction of an Underground CD station Turf City Station and a 3km bored tunnel towards CR205 King Albert Part Station.

The tunnel will be constructed with two slurry TBM. The contract also comprises a TBM launch shaft and a new road connecting the Station to Eng Neo Avenue.